Posted on: March 24, 2017

East 10th Street Project

The East 10th Street Project will begin April 3. Construction will take place in four phases that will require road closures and detour routes for each phase. Paul Reed Construction and Supply from Gering, NE will serve as the contractor.

The East 10th Street Project will include the removal and replacement of the existing pavement, alley and driveway approaches, curb and gutter, sidewalks, pavement markings and storm sewer inlets.  Construction of a 10-foot bicycle trail will take place on the north side of 10th Street from Flack Avenue to Meadowlark.  Placement of an on-street bicycle lane on 10th Street from Sweetwater Avenue to Flack Avenue will include the elimination of parking on the north side of 10th Street as outlined in the public outreach process during the design of the project.

The project phases will be as follows:

Phase 1 – Box Butte Avenue to Yellowstone Avenue
Phase 2 – Yellowstone Avenue to Grand Avenue
Phase 3 – Grand Avenue to Hudson Avenue
Phase 4 – Hudson Avenue to Flack Avenue

The detour route will be Third Street/Highway 2 via Box Butte Avenue and Flack Avenue/Highway 87.  Construction of the bicycle trail from Flack Avenue to Meadowlark will occur simultaneously with the project phases.  10th Street east of Flack Avenue will remain open at all times.

Additional Info...
Facebook Twitter Google Plus Email

Other News in City News

Overlay Process Delay

Posted on: June 23, 2017

Fireworks

Posted on: June 21, 2017

Landfill Passes

Posted on: June 21, 2017

Street Mill and Overlay Project

Posted on: June 21, 2017

Box Butte Avenue Streetscape

Posted on: March 31, 2017